News, updates, commentary and more from BikeAthens. BikeAthens is a 501(c)3 nonprofit organization based in Athens, GA. BikeAthens promotes transportation and land-use policies that improve alternative modes of transportation, including pedestrian, cycling, and public transit options. The mission of our organization is to make alternative transportation a practical, convenient, and safe option for all citizens of Athens-Clarke County.

Showing posts with label greenway. Show all posts
Showing posts with label greenway. Show all posts

Friday, January 8, 2010

Work begins on College Station Rd bridge!

At last:

Workers began clearing out trees this week to make way for a new bridge off College Station Road near Riverbend Road.

The bridge will provide access to an Athens-Clarke sewer treatment plant under construction beside the North Oconee River near Horsehoe Bend and will open up an adjacent tract of University of Georgia-owned land for development.

UGA and the Athens-Clarke government will split the $3 million cost of the bridge, said County Manager Alan Reddish.

Construction will take about a year, and the bridge will include bike lanes and a pedestrian walkway that Reddish said can be tied into the county's river greenway program.

-from the ABH

Tuesday, October 27, 2009

SPLOST projects submission workshops TODAY

Late notice, but heads up!

The SPLOST presents a great opportunity to propose bike, ped, and transit oriented projects, which will be funded by a 1 cent sales tax. The Multi-Modal Transit Center was funded by SPLOST!

Stay tuned for news on a BikeAthens-led brainstorming session. You can help us determine what projects we will submit for consideration. If you already have an idea, comment on this post or send us an email.

Sunday, October 11, 2009

Bus plans & greenway meetings

ABH Sunday reading:

A plan exists for improving transit, but will there be money to implement it?

Also, "the Athens-Clarke Leisure Services Department will hold two public meetings this week about its plans to build a greenway along the Middle Oconee River."

Tuesday, September 29, 2009

How a town becomes bike friendly

This video, from Bikes Belong, shows how Boulder, CO became bike friendly (and how Athens could too):



Boulder Bike Story from Bikes Belong on Vimeo.

Wednesday, July 15, 2009

Rail-Trail progress


Also from Flagpole, a nice status update on the rail-trail project:
" Long in coming, Athens-Clarke County’s rails-to-trails project has passed a major land-acquisition milestone and ought to have plans before the Mayor and Commission perhaps by year’s end. This first phase of the project will create a multi-use bike/pedestrian path along the old Georgia Railroad bed from downtown’s Multi-Modal Transportation Center through Dudley Park and then roughly parallel to Oak Street to the planned site of a park-and-ride lot where Lexington Road meets the 10 Loop."

The article pays particular attention to what remains of the "Murmur Trestle over Trail Creek—so named because a photo of it appeared on that R.E.M. album ... All along, the trestle has inspired the rail-trail project by offering a level route over steep topography into downtown."

Thursday, July 2, 2009

South leads in obesity rates

A recent nationwide study on obesity rates shows the southern U.S. still in the lead.

Aside from our country-fried diet of chicken and biscuits, our inactivity is a major factor in our collective girth. We've built our communities to accommodate car use, to the almost complete exclusion of enabling a walk or bike ride.

If we incorporate physical activity into our daily routines - commuting by bicycle, walking to and from the bus stop, spending weekends strolling greenways - we will make significant headway against the obesity epidemic. The best way to encourage walking and biking is to make it as safe and as convenient as driving, which means we need:

- an interconnected network of well-maintained bike lanes and greenways
- an interconnected network of well-maintained sidewalks and crosswalks
- a bus system that takes people where they want to go, when they need to go

While Athens-Clarke and UGA, especially, have made modest gains towards these goals, we are only half-way there. Many still feel unsafe riding a bicycle in Athens. Long stretches of foot worn paths evidence the need for more sidewalks.

As Jeff Levi, executive director of the Trust for America's Health, notes, the obesity problem is "not going to be solved in the doctor's office but in the community, where we change norms."

Wednesday, June 24, 2009

Greenway news

In "a couple of years," you'll be to walk/ride the Oconee River Greenway from Sandy Creek Nature Center to College Station Rd.

Thanks to the Greenway Comission for patiently pursuing the property for this extension!

Tuesday, April 14, 2009

UGA-ACC land deal opens door for greenway expansion

From the Banner-Herald:
The University System Board of Regents today should approve the University of Georgia's decision to donate 1.35 acres of land off East Campus Road to the Athens-Clarke County government.

[R]iverside acreage [will] extend the North Oconee River Greenway from Oconee Hill Cemetery all the way south to College Station Road.

Athens-Clarke will get land along the North Oconee River to extend the North Oconee River Greenway from Oconee Hill Cemetery to College Station Road. The planned bridge will allow cyclists on the greenway to get to bike lanes on College Station Road.

Tuesday, March 31, 2009

Local trans planning: get involved & be heard

MACORTS, the regional transportation coordination body, is currently updating its Long Range Transportation Plan.

It's a little difficult to find on the MACORTS main page, but the presentation given by the consultants who are handling the model for the LRTP is now online. The model is a representation, based on traffic conditions and socio-economic data, of the geographic distribution of traffic in the Athens region.

Here's the direct link to the model.

On the plus side, they've included public transit for the first time ever, so we may get a more accurate picture when we look at Athens Transit and UGA Campus Transit as part of the network. However, the 2035 projection was based on current ridership - today's raw numbers, not percentages - so with the projected 50% MACORTS-wide population growth and 47% UGA enrollment jump, this obviously needs some adjusting.

Stay tuned for information on how you can submit formal comments on the LRTP.

Wednesday, February 18, 2009

$500K available for alt trans projects in Athens

Athens-Clarke County has $500,000 to spend on bike, pedestrian, and transit projects, and we want to hear from you on which projects you'd like to see happen.

Read the post below and then please fill out the poll on our blog home page.

Details & project descriptions via the ABH:
A standing committee of five commissioners is deciding how to spend $500,000 the commission earmarked for alternative transportation - walking, biking and buses - in 2006.

Officials said they want to spend $75,000 to update a plan for future bike lanes written in 2001, expanding it beyond the three-mile radius from downtown that was mapped out eight years ago. They also want to hold back $25,000 for incidental expenses.

Projects that parks, transportation and Athens Transit officials said could be funded with the remaining money include:

► $400,000 to buy land for a future expansion of a planned, federally funded park-and-ride lot at Oconee Street and the Athens Perimeter.

► $400,000 to widen College Station Road between Research Drive and Barnett Shoals Road to add lanes for bike riders.

► $400,000 to build 1.3 miles of sidewalks along Oglethorpe Avenue, Whit Davis Road, Cherokee Road, Research Road and Cedar Shoals Drive.

► $400,000 to build a trail connecting the Multimodal Transportation Center to a planned rail-trail project in East Athens.

► $400,000 to supplement sales tax revenue earmarked for the North Oconee River Greenway.

► $400,000 to build paths in a proposed park along Pulaski Creek.

► $400,000 to build a bike lane along West Broad Street/Atlanta Highway from Alps Road to greenspace near the Middle Oconee River.

► $400,000 to build an off-road path connecting Milledge Avenue and Milledge Avenue Extension.

► $200,000 to buy land for bus shelters at stops where the local government does not own right-of-way.

► $50,000 to promote Athens Transit bus service.

► $20,000 to buy and install 40 bike racks around Athens.

Thursday, December 11, 2008

Downtown deck and other trans plans running behind

ABH reports on the delays facing the proposed downtown parking deck as well as the Pulaski Greenway and other projects:

A new downtown parking deck, delayed by negotiations with developers to form a public-private partnership, is running two years behind schedule.

Most of the 33 projects in Athens-Clarke County's $122 million of sales tax-funded construction projects are already done or will be completed on time, but the deck is one of a handful that have fallen behind.

If planning and construction went as originally planned, the deck at the corner of West Washington and North Lumpkin streets already would have opened; now it is scheduled to be finished in August 2011.

Nine other sales tax-funded projects - trails along Pulaski Creek and an unused East Athens railroad; police headquarters renovations; a computerized police dispatch and record-keeping system; a bridge to East Athens Community Park; bridge repairs; Solid Waste Department offices; a new Sandy Creek Nature Center wing; and a diversion center - also are running behind, SPLOST program manager Don Martin told commissioners at a work session Tuesday.

The delays are not unusual and are for "very valid reasons" such as negotiating with railroad companies to buy land, Athens-Clarke Manager Alan Reddish said.

Wednesday, November 19, 2008

More time to comment on the rail-trail plans

UPDATE:
Please submit comments by Nov 28.

Rail-Trail info packet and comment form (.pdf)
More info about the project


Many thanks to Dorothy for the following info:
Review Still Possible, Comments Still Welcome If you missed Tuesday night's public forum for the Rail-Trail Project yesterday afternoon, there is still an opportunity to review plans and displays downtown at City Hall (301 College Avenue). They will be available in Room 101 for the upcoming 10 days (which, due to the Thanksgiving holiday, may actually mean only through Wednesday Nov 26).Comments may still be made via the web by going to www.dot.ga.us and clicking on Public Outreach found on the Information Center dropdown menu. All comments will become a part of the project record. A few of the issues meriting discussion or comment involve the bridge crossings over the North Oconee River and Trail Creek (into and out of Dudley Park). In particular, the project managers would appreciate some public input on the possible fate of the historic Georgia Railroad wooden trestle (sometimes called the "Murmur" trestle, having appeared on an R.E.M. album cover). Among the options that are under consideration for the trestle are a rebuild and adaptive re-use, or a teardown and replacement with a new prefabricated bridge. There may also be some "hybrid" options that have not yet been defined.

Tuesday, November 18, 2008

FYI! Hearing on Rail-Trail today

The Banner Herald reports:

Athens-Clarke County is close to securing final approval to convert an abandoned East Athens railroad into a trail.

A state-mandated public hearing at 5 p.m. today at the Multimodal Transportation Center on East Broad Street is the final step before the state Department of Transportation releases a $1.2 million federal grant and allows Athens-Clarke officials to begin designing and buying land for the rails-to-trails project.

"We feel very confident this project is going to go forward and be successful," county Natural Resources Administrator Mike Wharton said.

County officials will seek input on plans for the trail, but those familiar with the project shouldn't expect to hear anything new.

If you are not familiar with the plans or if you want to tell the county to keep as much of the Murmur trestle as possible, you should definitely go!

Monday, November 10, 2008

Greenway Network Plan

Take a Look & Send In Your Comments

Athens-Clarke County planners are accepting feedback on the Greenway Network Plan, which will determine where and how additional bike/ped paths will be established. Please take a moment to look over the following documents and submit your feedback about the Plan:

Greenway Network Plan (.pdf)

Greenway Network Plan - Zone Map (.pdf)

Greenway Network Plan - Public Comment Form (.doc)

Wednesday, November 5, 2008

How to emulate Portland

This week, Flagpole columnist Kevan Williams describes a number of ways Athens could follow the lead of Portland, OR in improving pedestrian and bicycle infrastructure. New Commission, take note!

For the rest of us, let's make a concerted effort to tell MACORTS about our desire for this kind of sustainable transportation equality.

Excerpts:
In Portland, drivers stop at crosswalks, even without flashing lights and neon bollards. ... It would take a lot of enforcement to ingrain that pedestrians always have the right-of-way here in the South, but the payoff is worth it: it slows everyone down, and puts drivers in a situation where they ought to be looking for pedestrians, instead of driving through and idling in crosswalks while trying to turn.

Certain routes within Portland are designated as bike routes, regardless of the infrastructure in place. Even if there are no bike lanes or “sharrows,” a flat side street could be made an official bike route. Imagine if BikeAthens’ bike map were adopted by the city, and those routes which were good for bicycling were then signed by the city to guide bicyclists.

In Portland, what we would call greenway trails are considered an important transportation network, just like rail and roads. There is a comprehensive system of off-street bicycle trails, in some cases extending miles without crossing a street. These don’t just follow the rivers, but also rail lines, transmission lines, highways and other easements where access is already limited. Most importantly, these routes actually go places, and are fed by on-street bicycle routes in a logical manner.

Bringing It Home: Portland is a city that’s a lot like Athens; it’s not a metropolis of especially tall buildings, and its greatest strength lies in its walkable neighborhoods. Basic services in Portland can be reached by bicycle on a neighborhood scale just as easily as can thousands of workplaces downtown on a citywide scale. The neat thing is that most of it isn’t done through huge infrastructure and park projects; there seems to be a commitment to a bottom-up approach, which focuses on making neighborhoods and side streets safe to walk first, and then builds up into an entire city of cyclists. After all, if people don’t feel safe crossing the street at the end of their block, they won’t be biking across town on a greenway.

Full article here.

Sunday, November 2, 2008

Greenway Network Plan Public Meeting on Nov. 8

ACC Leisure Services will host a second public meeting regarding the Greenway Network Plan development on Saturday, November 8 at Fire Station #7 on Barnett Shoals Rd. from 10:00-11:30 a.m. For more information, call 706-613-3615 or visit www.accleisureservices.com.

Wednesday, October 1, 2008

Reminder: River of Bikes Ride tomorrow

River of Bikes Ride

In support of the eco-conscious touring practices of Okkervil River
(playing at the 40 Watt on 10/2/08), BikeAthens is organizing a twilight
group ride from downtown, along the Greenway, and back to downtown.
Afterwards, we'll convene at Max Canada's patio for refreshments before
the show.

The ride begins at City Hall at 7 pm - be sure to have a helmet, lights,
and water.

We hope to see you there!

Wednesday, September 17, 2008

Transportation news a-plenty in Flagpole

The Flagpole that hit the streets today is chock full of transportation-related articles: get up to speed on downtown parking rates, the Pulaski Creek Greenway, and plans for a downtown parking deck next to the Georgia Theatre.

There's also a humbly submitted comment piece by yours truly on sharing the streets. Enjoy!

Monday, September 8, 2008

New Rail-Trail/Greenway in Athens!

Great news in the ABH today!

Athens-Clarke officials are beginning to plan a new park and trail north of downtown Athens.

The $1 million Pulaski Creek Greenway would link the Athens Community Council on Aging, the Bethel Midtown Village housing project and the Pulaski Heights and Newtown neighborhoods, the Denney Tower retirement home, Lay Park and the North Oconee River Greenway.

"It gets into all the interconnectivity we've been talking about for years," said Kent Kilpatrick, interim director of the Athens-Clarke Leisure Services Department.

Officials will show preliminary plans to the Athens-Clarke Commission at a Tuesday work session and to the public Thursday at a 5:30 p.m. drop-in hearing at the council on aging. They call for a small park near the council on aging's Hoyt Street building and a trail running north along an unused railroad connecting to the North Oconee River Greenway near the College Avenue bridge crossing the river.